During FY'25, our Power Stations have achieved generation of 19 ,<strong>862 million</strong> units as against 21 ,773 million units generated in corresponding period of the previous year which is lower by about 9% or 1 ,911 Million units. This is mainly due to heavy flash flood in Teesta Basin in October'23 which has resulted into complete shutdown of Teesta -V Power Station
Our P lant Availability Factor for FY'25 stands at 73.94% against the corresponding previous period Plant Availability Factor of 77.60% which is about 4% lower.
During FY'25, Company has earned Revenue from Operation of Rs . <strong>8,994 Crore</strong> as against Rs. 8,397 Crore in the corresponding previous year which is about 7 % higher.
During FY'25, Company has earned PAT of Rs. 3,084 Crore as against Rs. 3,722 crore of corresponding previous period which is about 17 % lower.
all the 4 units of Parbati -II Hydro Electric Project (800 MW) have become commercially operational with 3 units from 1 st April'25 and 4 th unit from 16 th April'25.
NHPC has al so commissioned 107 MW out of 300 MW Solar Power Plant in Bikaner, Rajasthan under CPSU Scheme on 12th April'25 which is an important step in our ongoing efforts to diversify into other renewable energy sources.
In respect of Subansiri Lower Hydro Electric Project (2000 MW), the balance construction work at site is going on in full swing. Overall, 96% physical progress of the project has been achieved.
We are very hopeful of commissioning 5 units of the project in the current financial year and rest of the units by May'26.