Balasubramanian · Arihant Capital Markets
Sir, my first question, in passenger coaches side, we have seen significant improvement on the execution side. In this quarter, we did nearly 18 metro cars compared to last Q3 around 3 metro cars. Overall, in this 9 months FY '26, we did 39 metro cars, but we have guided 100 to 120 metro cars as our aspirational target by FY '26? So I'm trying to understand whether in Q4, we can make it 20, 25 additional metros, we can end up 60, 65 kind of range. And if you could share more details because we are running multiple projects, running concurrently, especially Pune aluminium, Gujarat, Mumbai, Bangalore and Vande Bharat. So could you please share a detailed time line of the production ramp-up of each major program?
Sure, absolutely. Thank you for your question. The target we had set for ourselves this year was between 100 to 120 cars. There is a significant improvement that we have made. We may not be able to get to 100 or 120, but we'll be pretty close to that. There will be a significant improvement in Q4. We have already started ramping up. In January, we were much higher than what we were in December, and we are looking at continuing the trend in February and March as well. Pune is an aluminium metro coach - production will start only after completion of the aluminium coach line - the car body production will start in Q3 or Q4 of this coming financial year. Vande Bharat production has already started. We expect by the end of this financial year, that is March 2026, to be able to complete the car bodies of the first rake, which is 16 cars. We are already in production. The first train is likely to be ready in Q3 of the coming financial year. Bangalore is continuously being executed, and Gujarat now has started execution. Mumbai will start execution from Q3 of the next financial year.
Aniket Madhwani · Steptrade Capital
My question was with regards to the new facility for components. So when it will be commissioned and in the line for backward integration you are planning?
So it is already going on, sir, both the expansion in terms of the aluminium that I mentioned, the backward integration for all the car body components and also the test track, which is going to be a big game changer for us, even for our ambitions to get into the high speed or the bullet train segment, the 1.6 kilometre test track. So all of that work is going on at full pace, and we expect all of these projects to be completed in the first half of the next financial year.
Aniket Madhwani · Steptrade Capital
And the orders from Vande Bharat will contribute from next financial year or you're expecting some of these to start by this quarter?
No. Some of them the dispatches will start only next financial year, but the production has already started. We would have completed the car bodies almost completed the entire car bodies for the first rake within this financial year. So to that extent, being a percentage of completion accounting, some revenue will likely flow in this quarter as well in this year itself also.
Anand Kulkarni · Front Wave Research
I have a couple of questions. First, how much is the backlog of CRRC, the Bangalore Metro? And when are we expecting it to be clear? Do we see any spill over in FY '28? That's my first. And second, what is your current production run rate for metros specifically?
So the backlog of CRRC is likely to be over in FY '27. At most, if it does, then it may be spilling over to the first month or first 1.5 months of the FY '28. But bulk of it will be over in FY '27. As far as the run rate of metro is concerned, last quarter, we improved. This quarter, we are further likely to improve. Our target is to get to 20 cars per month, which is what we will get within the next few months. So it is a process. It is a new business line, which we are ramping up. There are always teething troubles when you go for such a steep ramp-up. Most of them, we have been able to overcome. The result is already in front of us that the ramp-up is already visible.
Viren Deshpande · Alphapeak Investments
Sir, the execution has improved to some extent with the availability of the wheel set. And last time, you had mentioned that the imports have been permitted. So still, are we not in a position to execute to the fullest extent?
So import of wheel set takes a little bit of time once we get the orders, and this is only permitted for the NRC or the private sector wagon requirement, not for the wagons that we produce for the Indian Railways. So therefore, the even when we start import process, from the day we place the order till the time we receive the wheels and we are able to use, it takes between 4 to 5 months. So that's the reason we were unable to ramp up the production to the desired level. But right now, till we receive the new tenders to be able to produce around about 800 wagons is what we are targeting per month, and we should be able to get there. As I said, this was an unexpected blip that we faced from the rail wheel factory.
Viren Deshpande · Alphapeak Investments
But our production in the joint venture is expected to start from the next year Q1?
Yes. The trial production is expected to start by March or April and then stabilize in another couple of quarters. It's premature to say. The trial production will start now and then to stabilize whatever time it takes. It generally takes anything between 1 to 2 quarters.
Viren Deshpande · Alphapeak Investments
And regarding this Titagarh Firema joint venture, where they held about 41% stake. And I think the balance 59% was held by Titagarh, can you explain what is the situation now?
So our share Titagarh's share in Firema was minority. It was not 50 or whatever percent you were mentioning, sir. It was a minority shareholding and then there were other partners also in this. As far as the what we have already reported, the company had run into difficulties. There were two objectives of investing into Firema. One was to set up our business in India for the Passenger Rail Systems. And as you can very clearly see, that has met with thumping success. We have an order book of INR11,000 crores directly and about another INR7,000 crores indirectly through our joint venture with BHEL that is all in the passenger segment. So that has paid very rich dividends. The second one was to produce in Europe for Europe. That unfortunately could not succeed and the company continued to make losses. Now the Italian State Railways have made an offer to buy out that company, and that is a deal which is under progress.
Rajesh Bhandari · Nakoda Engineers
Sir, we have a total order book of around INR28,000 crores, INR27,755 crores in which we have for wagons 3,126. How much is the monthly load of the wagons?
Sir, this is almost like I said, for half of next financial year, we should be able to cater to with the existing orders. To go beyond, we are looking at the new tenders, including the new orders that we will be able to receive on account of this wagon leasing license that we have obtained.
Rajesh Bhandari · Nakoda Engineers
Till when are the government's wagon inquiries coming, sir? Sir, what is the positive effect of this budget? And what will be the positive impact of the trade agreements that we can expect in as far?
This is not in our hands, but we are expecting it to come in Q1. The railway is still determined that it will carry 3 billion tons of traffic by 2030. The vision that the Prime Minister said in the national rail plan, 40% market share will be in logistics. The budget is very positive. The first is for our business on the passenger rail system. The biggest thing the company is working on with great focus is additional high-speed corridors. 7 new high-speed corridors have been announced. Because Titagarh is the only self-reliant company, which can be called a make-in-India company, which has the capacity to build high-speed trains. As far as freight is concerned, there have been some media reports about some wagon procurement, which is there, which is about 30,000-32,000 wagons. But the railways have not officially confirmed that to us as of now. On the trade agreement: Neither positive nor negative. Trade agreement has no direct impact on our business, sir. Of course, it does improve the general sentiment. The indirect advantage that we will get is that if there is higher GDP growth, it is going to enhance the GDP growth and the size of the economy.
Parvez Qazi · Nuvama Group
Good afternoon, sir. Thanks for taking my question. So my first question is on the passenger business. I mean, we have multiple orders now. Based on your commentary, production on most of them will start at some point in FY'27. So are we looking for more orders in this segment? Or do we first want to stabilize and start work on the existing orders?
So, Parvez, we are absolutely looking at more orders. In the last 6 months or less than 6 months, I would say, we have booked orders of about INR 4,000 crores for metros, as you are aware, Mumbai Line 5 and Line 6. We are looking at participating in a spate of tenders that are in the offing. So in terms we are doing both simultaneously. We are continuing to build up our order book and participating in new tenders, and riding the wave of opportunity that this sector presents. Simultaneously, as we keep on building up our order book, we are also enhancing capacities.
Devanshi Shah · HUF Capital
First one being, what is the planned capacity capex allocation for FY'27? And how will it be funded, say, through internal accruals or debt?
The overall capex that we had announced for the Passenger Rail Systems to achieve the capacity or the production that we have projected right now was about INR1,000 crores. The capex that we are envisaging to make within FY'27 is within that amount. Part of it was funded through the equity raise that we had done and the internal accruals, and part of it through the funding, through the debt. So there is no new capital requirement per se that will be there, apart from the further expansions if we take up. If there are, for example, the expansions for opportunities like high-speed or MRVCs or some other additional large projects that come up, that may take up new capex requirements. But outside that, the current levels that we have, the current orders that we have will be catered to by the capex that was already announced, which is underway and will be completed in the first half of FY'27.