Ragini · Elara Capital
H1FY26 capex + FY27/FY28 guidance?
for this year the total capex which we have kept is around INR7,500 crore and out of that we have already spent in two quarters around INR3,600. So in the balance two quarters we are 100% sure that whatever capex we have given as a MOU target by Government of India, we will achieve very comfortably. As far as next year is concerned, '26-'27, we have kept a capex of around INR8,000 crore for the next year.
Ragini · Elara Capital
5 GW Arunachal Pradesh hydro pipeline progress?
In the 5 gigawatts, actually, there are five projects, in fact. And out of that five projects, three are still under PFR stage, which we call Pre -Feasibility Report stage. But regarding the two other projects, which one is the biggest hydro project in India, that is 3,097 megawatt, Etalin, and other is this around 688 megawatt, Attunli. So, these two are progressing well. And in case of Etalin, we have like, we are in the final stages of getting the forest, sorry, environment clearance. And we have already received in fact the forest and environment clearance.
Paras Chheda · Purpleone Vertex Ventures, LLP
Buxar commissioning + why revenue flat despite new project additions?
regarding Buxar, as I told earlier, that we are going to declare the commercial operation of the plant within one or two days because already full load operation has been completed. And regarding the second unit, during this financial year, we will be completing and declaring the commercial operation, may be January or February next year max