We are pleased to inform that the full capacity of 90 -megawatt Omkareshwar floating solar project has been declared as commercial operational with effect from 30th October 2024.
Further, consequent upon successful commissioning of Raghanesda Solar Power Project 100 megawatt, the commercial operation date, COD for the balance 42 megawatts out of the 100 -megawatt capacity was declared in the third quarter of current financial year on 12th October 2024. With these additions in operating assets, total installed capacity of SJVN now stands at 2,466.5 megawatts.
One of the major developments in this quarter is the signing of an MOU with the Government of Bihar on 31st December 2024 for development of 1,000 -megawatt Hathidah Durgawati Pumped Storage Plant in Bihar. The project cost is estimated at INR<strong>5,663 crore</strong>s with a levelized tariff of INR9.39 per kilowatt hour.
Another important development is the MOU signed with the Energy Department, Government of Rajasthan on 20th November 2024 for the development of renewable energy in the state. Under this partnership, SJVN will develop 5 gigawatt pumped storage projects and 2 gigawatt floating solar projects in Rajasthan.
The boiler light -up for Unit 1 of Buxar Thermal Power Project, which is having a capacity of 1,320 megawatt of 2 units, 660 megawatt each was successfully achieved on 2nd October 2024. The project of these 1,320 megawatts will generate <strong>9,828 million</strong> unit of energy with 85% of this power being utilized in the state of Bihar. our prestigious 1,500 megawatt Nathpa Jhakri Hydro Power Station achieved 6,830.242 million units by the third quarter of financial year 2024-'25 compared to 5,731.078 million unit by the