Q1FY27 record PAT INR4,867cr (+47% YoY).
- Nuclear power technology fuel — answer hedged.
- Nuclear ordering timeline 2035 — answer hedged.
- Qip use case deployment — answer hedged.
On nuclear, you are targeting 10 GW by 2035. Details on technology tie-up, domestic vs imported technology, fuel sourcing, and when first plant can be expected?
It depends on government guidelines - rules under the Act have not been notified yet. We are evaluating both domestic and foreign technologies, decision will depend on per-MW cost. Sites are being made ready and studies are being carried out. As soon as rules come, we can move fast.
Nuclear target increased from 5 to 10 GW by 2035 - when will you order plants to commission by 2035?
Ordering can happen only when rules from Government of India come. Execution timeline for a nuclear plant should be at least 5 years by our standards.
The board has approved an equity raise - any specific use case for capital deployment?
The QIP is an enabling provision requested through EGM. We have a massive capex program of more than INR2 lakhs crores. Internal accruals are significant but interim gap between cash accruals and capex is being met through shorter-term debt. The QIP is an enabling provision for when needed.
What is the expected execution timeline for the QIP and how should we model the resulting per share equity dilution?
As of now this is an enabling provision with shareholder approval through EGM. The timeline, we will communicate it as and when it will be finalized. As and when there is a need for raising funds and the market opportunity also presents itself, we would come out with our plans and announcement at that time.
Do we have a capital allocation plan in place for nuclear for the next 5 years?
For nuclear, we have only stated our intention. Until Government of India notifies the rules, we cannot decide investment amounts or commissioning timelines. We are waiting for about 6 months for the rules to come but they have not come yet.
The EBITDA bridge shows a gain of INR2,200 crores due to change in fuel cost - is this from indexation of variable tariffs rather than actual fuel costs coming down?
Volume has increased, imported coal indices are higher, and merchant prices have also increased.
Can you share commercial terms of the 570 MW Bhutan hydro PPA and future plans?
PPA is yet not finalized. When finalized we will share. Regulatory structure - cost-plus or fixed tariff - is also yet to be finalized, whatever is the best opportunity will be captured.
Will Jaiprakash be consolidated in accounts and do you have expansion plans at Nigri and Bina? What will you do with the 11% shareholding at Prayagraj?
In JPVL, we have taken a 24% stake; for accounting it is an associate - we consolidate our percentage of profit. P&L and balance sheet are not consolidated, only the share of profit. At Bina and Nigri, good land is available and could be used for thermal or nuclear expansion in future.
What are the receivables from Bangladesh PPA and the year-ago number?
As of June 30, 2026, receivables are near about USD400 million and we are receiving on average USD100 million per month from BPDB. There is significant reduction quarter-on-quarter vs the all-time high in June last year.
You highlighted an incremental 3 GW capacity plan - can you elaborate? Will it be captive for group companies or more bids expected?
Part of the 3 GW can come from the 24% stake in JPVL (2,220 MW). Additionally, many states are facing power deficits and contemplating thermal bids. The additional 3 GW is planned for state-specific locations where new bids may come; it is at planning stage only.
Can you provide generation numbers and realized tariff for Godda in Q1FY27?
Generation in Godda for Q1FY27 was 2.519 billion units vs 2.362 billion last year. Total revenue for Q1 was INR2,473 crores vs INR2,135 crores same quarter last year.
Does Adani Power have any PPA arrangements similar to Adani Green with Adani Energy for the energy management solution business?
Neither do we have any agreement with Adani Green Energy nor with PTSL. We don't have any PPAs with Adani Energy.
What was merchant capacity in Q1FY27 vs Q1FY26? Was merchant capacity converted to PPAs?
Merchant capacity has reduced. Butibori and Tuticorin plants were on merchant basis earlier, now under PPAs. Merchant volume was 4 billion units in Q1FY27 vs 6 billion units in Q1FY26 - a one-third reduction - along with capacity reduction in open capacity.
Maharashtra approved a PPA sold to Adani Energy Bombay with Adani Power supplying 540 MW thermal - how does this RTC contract work for Adani Power?
It will be a PPA based on capacity charges, not just units sold. The RTC exposure is taken by PTSL. For Adani Power, the contract structure is exactly like a typical PPA - we get fixed charges and the ramp up/down volatility is handled by the other party.
Over the next 2-3 years with large expansion and acquisitions, how will net debt-to-EBITDA move and what is guidance?
Annual FFO is INR20,000 crores. Over the capex program period, FFO will be more than INR1.4 lakh crore vs INR2 lakh crore capex. Interim requirement of around INR60,000 crores from debt. Net debt-to-EBITDA is slightly higher than 2x now and will not cross 3x at any point.
With 13.2 GW bids in market and 11.1 GW untied, which states will bid close this fiscal? And on the 2.5 GW MSEDCL RE RTC contract - is it captured in the PPA tie-up bucket?
Active bids: UP 4,000 MW, Gujarat 4,000 MW, Uttarakhand 1,320 MW, West Bengal 3,800 MW - about 13,000 MW total. The 2,500 MW MSEDCL is a supply contract needing minimum 51% green - multiple sources will serve it through a trading platform.
In FY27 and FY28, which quarters and which plants are 1,320 MW and 1,600 MW expected to commission?
Korba Phase-II will come before December end this year. Mahan Phase-II first unit expected in Q1 of next financial year, second unit with 6-month gap in Q3 (but trying to bring it to Q2).
What will be the annual capex run rate for next 2-3 years?
FY27 expansion capex near about INR25,000 crores. FY28 near about INR33,000 crores. Thereafter more than INR35,000 crores.
Regarding the proposed 3 GW addition - is the capacity from Jaiprakash currently under PPA or open?
The 3 GW is at a planning stage for future state bids - capex and equipment ordering not yet firmed up. As regards JPVL, we have 24% stake and if we get opportunity to increase stake, we will take it forward. No PPAs tied up yet.
The Korba PPA has not been signed yet - will it be supplying under PPA or merchant market after commissioning in December?
Even if a PPA is signed during the current year under long-term bids, there would be some period of maybe a year or two in merchant market from this capacity. We have participated in a bid where results are pending, and we hope to tie up capacity in the current year.
Is the 180 MW Jaiprakash plant operational? Will it contribute to financials from Q2 onwards and is it tied up under any PPA?
It is not operational - similar condition to what we acquired in Butibori. Will take about 6 months to revive. We don't foresee much contribution during the current year. Not tied under any PPA.
Continuing EBITDA grew 22% with only 4-5% capacity increase and merchant revenues largely flat - what explains the strong EBITDA increase?
Revenue consists of two parts - capacity charges and energy charges. Tuticorin and Raipur conversions from merchant to PPA brought significantly higher capacity charges. Energy charges also higher due to imported coal indices. Altogether volume increase, higher capacity charges and energy charge contribution drove the EBITDA improvement.
Can we expect dividend or bonus given sufficient reserves?
We have a huge capex program for the next 6-7 years. We are reinvesting in the capex program as return on capital is quite good. We are giving more capital appreciation than dividend and therefore reinvesting whatever surplus we are generating.
Have we considered Bangladesh disputable portion in results?
No, we are not considering whatever is disputed. We are considering as revenue only that which is not disputed.
What are the major short-term catalysts and risks for the company in the next 6-12 months?
95% capacity is tied up in long-term PPAs with DISCOMs, only 5% open capacity. Two-part tariff mechanism provides stable EBITDA. Q1 is typically peak because of high temperatures. As monsoon rains arrive, power drawdown goes down a little. With largely long-term contracts, we expect stability in revenues and EBITDA.
Company guided INR25,000 crores capex in FY27 and INR33,000 crores in FY28, and proposed INR15,000 crores equity raise. Has anything changed in capex plan or is this preparation for expansion beyond 23.7 GW?
No change in the capex program. Very firm and confident on INR2 lakhs crore capex in defined timeline. INR25,000 crores this year, INR33,000 crores next year, more than INR35,000 crores thereafter. Internal accruals will fund majority of capex; interim gaps funded from debt. Target is now 45 GW (revised from 42 GW) on same timeline.